Kouvola.

45 MW on paper.
What fits on the land?

Illustrative three-dimensional model of the proposed two-building Kouvola data center campus
Illustrative campus concept on the mapped Kouvola parcel. Building form, planting and neighbouring heights are not a measured survey.

Kouvola, Finland · Site and campus study

The expensive choice appears before the first building is designed.

On a real 11.14-hectare parcel, Earendil compared three layouts for the same proposed data center programme. Each was tested against 34.2 MW of IT load. Under the study's parking allowance, the two-building option keeps all 304 spaces at ground level. The two four-building options place 288 of those spaces in a parking structure.

The building count changes what must be built on the land. It is a consequence worth seeing before committing to the next design stage.

Kouvola is Earendil's public reference case. The 45 MW incoming electrical programme is a design scenario; grid capacity and development approvals remain to be established.

2020 aerial photograph with the 11.14-hectare Kouvola cadastral parcel outlined
01 / The real parcel2020 Kouvola orthophoto and NLS cadastral boundary. See the source drawing ↗

The land has to carry the entire campus.

The cadastral area is only the starting point. The site study maps 6.03 metres of ground relief and tests three platform levels over the same footprint. At 57 metres, its indicative calculation gives 93,600 m³ of cut and 3,300 m³ of fill. At 59 metres, it gives 13,500 m³ of cut and 77,100 m³ of fill. These screening calculations exclude stripping, bulking and settlement. They show why building levels should be tested before they are fixed.

Kouvola terrain map and indicative cut-and-fill quantities at platform levels of 57, 58 and 59 metres
02 / Ground levelsThree levels, one test footprint. Indicative quantities, not an earthworks estimate. See the source drawing ↗

Water and ground conditions also claim space. A municipal planning report describes a large ditch carrying runoff from upstream areas. A regional geological map places much of the studied parcel in a clay class; its scale calls for a ground investigation before foundations are designed. The study reserves land for drainage rather than drawing buildings across it.

Power nearby is a question, not an allocation.

A mapped 110 kV enclosure lies close to the parcel, but proximity establishes neither available capacity nor a connection route. The electrical analysis turns the proposed 45 MW incoming programme into 34.2 MW of studied IT load using an explicit 5% reserve and a peak design factor of 1.25. Those assumptions make the layouts comparable.

03 / The layout decision

Same programme.
Different land consequences.

The first study examines 30, 45 and 60 MW electrical programmes and takes 45 MW forward as the central case to test. The siting study compares three configurations at the same IT load and data center floor area: two buildings of 120 × 60 metres, four aligned pavilions of 80 × 45 metres, and four staggered pavilions of the same size.

Three equal-programme Kouvola layouts: two buildings, four aligned pavilions, and four staggered pavilions
03 / Three alternativesA, B and C tested on the same parcel and 34.2 MW IT programme. Swipe the plans to compare. See the source drawing ↗
Equal programme, different consequences
A · SelectedB · AlignedC · Staggered
Buildings2 × 120 × 60 m4 × 80 × 45 m4 × 80 × 45 m
IT load34.2 MW34.2 MW34.2 MW
Car parking304 at ground level304 total; 288 in structure304 total; 288 in structure
Minimum building separation40 m20 m20 m

Comparison from Siting & Architecture, p. 10 ↗. B and C are envelope comparisons; their internal plans were not developed to the same level as A.

The study selects the two-building scheme for the next design stage. It reduces fragmentation and keeps the parking programme at ground level. Four pavilions could still suit an operator that needs four independent building units.

For a landowner or developer, the useful outcome is a preferred configuration, the reasons for choosing it, and the facts that could change the decision. Kouvola makes those reasons inspectable across a 40-page site study, a 29-page siting study and a 36-page 3D masterplan. The same parcel boundary carries through terrain analysis, alternatives, equipment areas, circulation, plans and sections.

Illustrative overhead view of the selected two-building campus masterplan
04 / A basis for the next stageBuildings, yards, drainage, access and landscape in one concept. See the source drawing ↗

Spend next on the facts that could change the answer.

The next work is clear: qualify land rights and planning rules; seek an actual power offer; survey utilities, ground and drainage; and test access, noise and fire requirements. Option A provides a basis for that work.